BAUER Technologies Ltd tendered for and won the £15 million contract for the piled foundation of the new structure. The Power Station consists of two power generating units, each comprising a variety of sub-structures, covering an area of 60,000 sqm. The scope of the piling contract involved the construction of the piling platform, a preliminary pile testing regime, the erection of an on-site concrete batching plant, the installation of the piled foundations, comprising 439nr 620mm diameter bored piles, 426nr 800mm diameter bored piles and 711nr driven cast iron ductile piles and all piling attendances.
The foundation design was carried out by SIEMENS. The bored piles are designed to extend through 8m of Made Ground, 13m of very soft to soft peaty/organic Alluvium, 2m of dense to very dense River Terrace Gravels, and into the bearing layer of very weak to weak Mercia Mudstone. All bored piles were installed using up to 27m of segmental casing and extend to a designated minimum toe level. The average total bored length of the piles was 31m. The ductile piles were designed to be driven to refusal either into the River Terrace Gravel layer or the Mercia Mudstone. The preliminary pile testing regime confirmed the initial design.
Technical challenges involved drilling through existing obstructions of varying nature, i.e. brick walls, reinforced concrete slabs, existing old driven piles etc., and installing piles with cut off levels up to 7m below piling platform level. Due to the proximity of some cut off levels the reinforcement design had to be changed to allow for couplers at the top of the cage. Severn Power CCGT Project: Newport, United Kingdom
Piling commenced in August 2008 with three BAUER BG piling rigs
working simultaneously. The rigs on site were soon joined by another
three additional BAUER BG rigs, giving a total of six piling rigs at the
project's peak time (4nr BG 28, 1nr BG25 and 1nr BG24). Up to 85
people were working for BAUER at the peak of the project.
The project was completed under budget and ahead of schedule.
| Client: | Welsh Power / Severn Power, represented by Mott McDonald |
| EPC Contractor: | SIEMENS Power Generation |
| Piling Contractor: | BAUER Technologies Ltd |
| Contract Period: | May 2008 to March 2009 |
| Scope of Works (BAUER) and performance: | 60,000 m2 piling platform Preliminary pile testing 439nr 620mm dia. bored piles 426nr 880mm dia. bored piles 711nr driven ductile piles |
| Turnover | £12.5 million |
| Equipment: | 4nr BG28, 1nr BG25, 1nr BG24, 2nr ductile piling rigs |